Kitchen renovations have the widest price range of almost any domestic job — from a £3,000 unit replacement to a £60,000 bespoke refit. The difference is almost never about the building work. It's about the kitchen itself. This guide covers how to price the building and fitting work correctly, and how to handle the relationship between your labour costs and the kitchen supply.
These are labour and fitting costs only — the kitchen units, worktops, and appliances are separate unless you're supply-and-fit.
| Type | Labour cost range | Notes |
|---|---|---|
| Basic unit replacement (same layout) | £1,500 – £3,000 labour | Like-for-like swap, no structural changes |
| Full refit (same layout) | £3,000 – £6,000 labour | Strip out, new electrics and plumbing, fit new kitchen |
| Layout change (move sink or appliances) | £5,000 – £9,000 labour | Drainage and electrical rerouting adds significant cost |
| Extension or structural opening | £8,000 – £20,000 labour | Opening a wall, adding bifolds, extending into rear |
Decide early whether you're supplying the kitchen or fitting one the customer has bought. Both are legitimate models, but they have different implications. Supply-and-fit gives you more control over quality and schedule (you're not waiting for a customer's delivery), and you can mark up the units. Labour-only is simpler but means you're dependent on the customer getting the right items delivered on time — which they frequently don't. If doing labour only, state clearly in your quote that delays caused by late or incorrect deliveries will be charged at your day rate.
| Trade | Days | Notes |
|---|---|---|
| Kitchen fitter / carpenter | 3 – 7 days | Unit assembly, fitting, worktop templating and fitting |
| Electrician | 1 – 2 days | Rewire circuits, add sockets, cooker circuit, extractor |
| Plumber | 1 – 2 days | Sink, dishwasher, fridge water feed |
| Tiler | 1 – 3 days | Splashback. Often done after units are in. |
| Plasterer | 0.5 – 1 day | Making good after chasing and removal of old units |
| Labourer | 1 – 2 days | Strip out, waste removal |
Get the kitchen delivery date confirmed before you book the job in. Most delays on kitchen refits happen because units arrive late, damaged, or with missing items. Build a buffer of at least two days between delivery and your start date.